A company has two types of machines, type R and type S

by Guest Sat Nov 10, 2007 10:24 am

Could please somebody explain solution of the problem?

A company has two types of machines, type R and type S. Operating as a constant rate, a machine R does a certain job in 36 hours and a machine of type S does the same job in 18 hours. If the company used the same number of machines to do the job in 2 hours, how many machines of type R were used?

A. 3
B. 4
C. 6
D. 9
E. 12

The correct answer is C. 6.

Thanks!
Amit
 
 

Re: A company has two types of machines, type R and type S

by Amit Sun Nov 11, 2007 8:44 pm

Guest Wrote:Could please somebody explain solution of the problem?

A company has two types of machines, type R and type S. Operating as a constant rate, a machine R does a certain job in 36 hours and a machine of type S does the same job in 18 hours. If the company used the same number of machines to do the job in 2 hours, how many machines of type R were used?

A. 3
B. 4
C. 6
D. 9
E. 12

The correct answer is C. 6.

Thanks!


Machine R can do 1 job / 36hrs. S does 1 job / 18 hrs. We want the total to be 1 job / 2hrs

So this is the equation where x represents the number of machines you need:

rate of R + rate of S = rate of total
x/36 + x/18 = 1/2
(multiply all by 36)
x + 2x = 18
3x = 18
x = 6 machines
RonPurewal
Students
 
Posts: 19744
Joined: Tue Aug 14, 2007 8:23 am
 

by RonPurewal Fri Nov 16, 2007 6:47 am

That's it.

There are some ways to streamline this problem - such as using a 'rate chart' with (work rate) x (time) = (total work done) - but the essence of the problem will still be exactly what's here.
Guest
 
 

by Guest Wed Nov 21, 2007 7:26 pm

I have it is saying how many type of R machine used. I presume 6 means ( same no. of S + same no. of R)


so total number of R machine should be 3. Please correct if I am wrong
Guest
 
 

by Guest Wed Nov 21, 2007 8:12 pm

Let me correct I post wrong 3 Answer is 6

It is like this

In 12 hours R + S can finish a job

so in 1 hours the set finish 1/12 of the work

in 2hours the set (R + S) finish 1/6 of the work

so inorder to finish full work we need 6 sets of (R+S).
Hence R machine needed R=6
RonPurewal
Students
 
Posts: 19744
Joined: Tue Aug 14, 2007 8:23 am
 

by RonPurewal Thu Nov 22, 2007 3:47 am

Yep - if you look at the setup of the algebra done earlier in the post, you'll notice that the equation includes 'x' of machine R *AND* 'x' of machine S.
Guest
 
 

by Guest Tue Nov 27, 2007 12:39 pm

When I set this problem up I had it like this: x/36 + y/18 = 1/2. Where x and y where the number of each type of machine.

If the company used the same number of machines to do the job in 2 hours, how many machines of type R were used?

Where it says same number of machines, can that be interpreted as the same number of machine r as the number of machine s?

Kind of crucial wording that totally screwed me up.[/b][/i]
RonPurewal
Students
 
Posts: 19744
Joined: Tue Aug 14, 2007 8:23 am
 

by RonPurewal Fri Nov 30, 2007 5:16 am

Anonymous Wrote:Where it says same number of machines, can that be interpreted as the same number of machine r as the number of machine s?


I'm assuming that was a typo - a 'streamlined' version of the original question that obfuscates its original meaning. Interestingly, I didn't even notice that when I responded to this thread earlier.

Moreover, that's what the problem has to mean; otherwise, there are many combinations of machines that will solve the problem, as machine S is exactly twice as fast as machine R: we could just take away one machine S and replace it with two R's (or vice versa), and the new combination would also work. Since this isn't data sufficiency (i.e., we need a UNIQUE solution), that won't do.
Guest
 
 

by Guest Sun Jun 15, 2008 6:44 pm

------------1 machines-----1 machines
Rate-----------Rr---------------Sr----------

Time --------36----------------18---------(hrs)

Work--------1 job-----------1 job

W=rt

1*36*Rr=1*18*Sr

Sr=2*Rr

------------x machines-----x machines -----(Same machines)
Rate-----------Rr---------------Sr----------

Time --------2----------------2---------(hrs)

Work--------1 job-----Total work done by both machines

Work=2*Rr*x+2*Sr*x
=2x(Rr+Sr)
=2x(3Rr) ---Since Sr=2Rr
=6xRr

6xRr=36Rr ---job done by Rr from step 1

 x=6
mathmaster
 
 

R&S

by mathmaster Wed Jun 18, 2008 4:11 am

assume the task is to lay bricks so R - 1 brick per hour =36 hours : s 2 bricks per hour = 18 hours the ratio is 2:1

hence inorder to do the job in 2 hours need to lay 18 bvricks per hour in the ratio 1:2 hence the answer is 6
RonPurewal
Students
 
Posts: 19744
Joined: Tue Aug 14, 2007 8:23 am
 

by RonPurewal Wed Jun 18, 2008 5:19 am

nice wealth of solutions to this problem.
sweetness
Guest
 
 

by Guest Mon Aug 04, 2008 1:21 pm

m seein complex solutions here :)
in one hour machine a does 1/36 B does 1/ 18
one hour combined 1/36 + 1/18 = 1/12 ----> 1 hour
2 hours amount of wok done = 2/12 == 1/ 6

since num of machines is the same it shud be 6 .....
RonPurewal
Students
 
Posts: 19744
Joined: Tue Aug 14, 2007 8:23 am
 

by RonPurewal Wed Aug 13, 2008 3:37 am

Anonymous Wrote:m seein complex solutions here :)
in one hour machine a does 1/36 B does 1/ 18
one hour combined 1/36 + 1/18 = 1/12 ----> 1 hour
2 hours amount of wok done = 2/12 == 1/ 6

since num of machines is the same it shud be 6 .....


this is a nice compact solution.

next time, please write out words in full, so that your posts are easier to read. thank you.
alexei600
Course Students
 
Posts: 33
Joined: Sun Mar 14, 2010 4:39 pm
 

Re: A company has two types of machines, type R and type S

by alexei600 Wed Feb 09, 2011 1:48 pm

Instr.
When I do (1/36+1/18)*2=1/6
Combined rates of each mach. respect. mult. 2 hours. How can I derive from 1/6 , 6 machines?
Thanks
RonPurewal
Students
 
Posts: 19744
Joined: Tue Aug 14, 2007 8:23 am
 

Re: A company has two types of machines, type R and type S

by RonPurewal Fri Feb 11, 2011 6:12 am

alexei600 Wrote:Combined rates of each mach. respect. mult. 2 hours.


i don't know what this is supposed to say; please re-type your post in complete sentences, with words that are not abbreviated. thanks much.